We had a lot of fun building this house. It is an enclosed shell. The Hudson's are such nice people, we really enjoyed working with them on their home. They have become our friends and we look forward to visiting them soon. ♥

NOTE: The first pictures are at the bottom, scroll down! We took pictures almost every day to show the progress of this beautiful home.

Finished Home
 

August 26, 2002 ~ The sealer is on, we're done!
   

This is my favorite picture, through the trees!
 

The Hudson's wanted a unique, rustic stairway (left). The stringers are made from a single cedar, split in half. The stair treads are 3" thick planks of red cedar! (right)View from loft.
   

August 12, 2002 ~ Hello, camera difficulties have been resolved, now lets get caught up on the work done during the past month!
   

View through the trees & from the back. Notice the basement wall (made of ARXX insulated concrete) will have log siding on the outside that exactly matches the profile of our full log walls above. Some of the log siding is installed in these pictures.
 
   

Wrap around porch!
   

Beams finished!
   

Don't they have a WONDERFUL view????
 

July 24, 2002 ~ Sorry we haven't updated for a while. My camera has been acting up! We have got the porch flooring down, all the windows installed, and most of the log siding on the gables! We're almost done with our part of the work. I will get some new pictures up as soon as I can. :)Debbie

June 23, 2002 ~ Hello to all the Hudson's relatives! It's nice to know you are all following the progress!!
   

 

June 21-22, 2002 ~ porch floor joists. This home will have a porch wrapping around 3 sides, and a greenhouse is planned for the fourth side!!
   

June 20, 2002 ~ porch floor joists.
 

June 19, 2002 ~ sheeting gables.
 

June 13-14, 2002 ~ sheeting & tar paper. This home is going to have a metal roof installed by a roofing contractor.
   

June 12, 2002 ~ sheeting
   

June 11, 2002 ~ sheeting
 

June 10, 2002 ~ RAIN!

June 7, 2002 ~ gable & side porch rafters
   

June 6, 2002 ~ side porch beams & frame gable
   

June 5, 2002 ~ side porch posts
 

June 4, 2002 ~ back porch beams & rafters
 

June 3, 2002 ~ back porch posts
 

June 2, 2002 ~ front porch rafters
 

June 1, 2002 ~ front porch posts & beams
 

May 26 - 28, 2002 ~ pour piers for porch posts & frame dormer
 

May 22, 2002 ~ All rafters installed!!
   
   

May 21, 2002 ~ rafters
   

May 20, 2002 ~ rafters
   

May 19, 2002 ~ getting ready for rafters
 

May 15, 2002 ~ All beams installed!!
     

   

May 13, 2002. Some beams installed!
   

Here are the beams. They are western cedar. They used to be telephone poles for the railroad company, but they didn't need them anymore and the poles were reclaimed and re-sawed by a mill in Minnesota, owned by Brenda Hudson's uncle!
 

May 6-8, 2002. Interior stud walls...
 

May 3, 2002 ~ LOG WALLS COMPLETE!!
view from front (left) view from north east side (right)
   

April 30, 2002 ~ logs....
view from front (left) view from north east side (right)
   

April 29, 2002
   

April 28, 2002
   

April 27, 2002 ~ rained all day! :(

April 26, 2002
   

April 23, 2002 ~ put up logs until we ran out. Going home tonigt to get another load of logs.
   
view inside (left) and (right)
   
Kyan, Koda, Kaleb, and Kalee! (left) Kyan with a bunch of mushrooms he found! (right)
 
 

April 22, 2002 ~ dry enough! Logs going up again.
view from north east side
 

April 21, 2002 ~ rained all night, wet all day. No progress. :(

April 20, 2002
   

April 19, 2002 ~ back to work!
view from north east side
 

April 16, 2002 ~ third row complete all the way around. We "bugged out" just as the first raindrops hit. Heavy storms expected tonight, we're going home for a couple days!
   

Our home away from home!
"home" (left), "office" (right)    

April 15, 2002 ~ 3 logs high, half way around!
   
view from back
 
detail of subfloor with rods installed (left) first & second row of logs (right)
   

April 14, 2002 ~ rods installed, ready to start putting up logs in the morning!
   

April 11, 2002 ~ completed subfloor just before the rain hit! Aaah, spring!
   

April 10, 2002 ~ floor joists
 

April 9, 2002 ~ floor joists
 

April 8, 2002 ~ RAINED OUT!

April 6, 2002 ~ began construction, set beam!
The Hudson's chose to use "Arxx High Performance Wallsystem" (formerly "Blue Maxx") insulated concrete walls for their basement. It looks like really good stuff! ARXX WEB SITE
view from front (left) view from rear (right)
   

March 20-23, 2002 ~ milling the logs
   